Thursday, 15 December 2005

King's College Hospital - London
The project scope for our second visit was to supply and install a further 130m of VC constant wattage tape to frost protect pipework on the roof area.

Wednesday, 14 December 2005

Rosser & Russel - Basingstoke
Supplied and installed a temperature maintenance system on the hot water pipework in the ground floor toilets.

Friday, 9 December 2005

East Peckham WWTW
Supplied and installed frost protection trace heating and thermal insulation to the primary settlement tank within the de-sludging pumping station.

Wednesday, 7 December 2005

Marco's Leisure Ltd - Edinburgh
Supplied and installed 540m VCBOJ constant wattage tape to provide frost protection to the chilled water pipework.

Monday, 5 December 2005

Ironbridge Power Station
For this local project within the picturesque village of Ironbridge, ESH supplied and completed the installation of a temperature maintenance Trace Heating system for a heavy fuel oil supply pipe line. In total 700m of HFO supply pipework need to maintain +55°C.

King's College Hospital - London
Supplied, installed and commissioned trace heating tape to frost protect 30m of 2" pipework on the roof area.

Thursday, 24 November 2005

Eggborough Power Station 
Supplied 1000m of SCB50 constant wattage heating tape to this project.