Thursday 24 November 2005

Eggborough Power Station 
Supplied 1000m of SCB50 constant wattage heating tape to this project.

Wednesday 23 November 2005

New Ikea Store - Milton Keynes
Project scope was to supply and install trace heating tape for the provision of frost protecting the following pipework and vessel: 

  • 70m of chilled water supply
  • 30m of hot water pipe
  • one vessel 1.5m diameter x 1.8m in length

Monday 21 November 2005

Mynydd Clogau Windfarm Site
Supply and installation of both trace heating and armour flex insulation to 100m of 35mm plastic water pipe.

Wednesday 16 November 2005

Spray Plant 2K Ltd - Leeds
Designed and supplied a large metal clad drum heater 2000w 240v.

Monday 14 November 2005

Sunrise Senior Living - Edgbaston
Provided frost protection to the cold water pipework on the roof area. Supplied and installed 200m of VC12/2 trace heating tape.      
Premier Foods - Knighton
Designed and supplied a Bio-flex PTFE lined smooth 1.5" bore, 1.3m long  flexible heated hose, for the use on cold water male and female stainless steel fittings.

Friday 11 November 2005

Cookstown Creamery 
Supplied 330m of VC20 constant wattage trace heating cable to maintain a temperature of 50°C on 50mm pipework.

Tuesday 8 November 2005

Precision Antennas Ltd - Stratford Upon Avon
Designed and supplied 5 x 1.8m/2.2m edge panels (set of 4) and 5 centre panels of the same dimensions, designed to fit to the rear of Satellite Receiving Dish Aerials to prevent ice formation.

Wednesday 2 November 2005

Wath Central Junior School
Supply tools, materials and labour to install and test a frost protection system on two cold water circuits.