Tuesday, 23 August 2005

King's Wood School - High Wycombe
For part 2 of this project, ESH supplied and installed an additional 40m of H2OWAT55 onto the hot water pipework.

Thursday, 11 August 2005

Giggleswick Primary School
Supplied and installed 95m of H2OWAT55 self regulating heating tape for the maintenance of the hot water systems.

Monday, 1 August 2005

Tessenderlo Fine Chemicals Ltd - Leek
Supplied and installed trace heating to a stainless steel tank in a Zone1 Hazardous Area Gas Group IIB / T2.

Friday, 29 July 2005

Linthorpe Medical Centre - Middlesbrough 
Supplied and installed a self regulating frost protection trace heating system to the external chilled water services, low pressure hot water and mains cold water pipework.

Wednesday, 27 July 2005

Willington Quay - Wallsend
The project scope was to trace heat a large grease tank, to maintain a temperature between 100°C - 110°C. This required supplying and installing 300m of SC heating tape.

Thursday, 14 July 2005

Ikea Store - Milton Keynes

For this project we supplied and installed Trace Heating tape for frost protection on the chilled and hot water pipeworks, this also included a 1.5m by 1.8m vessel.

Friday, 8 July 2005

PPL Crompton Urethanes - Banbury
Supplied and installed trace heating for the purpose of maintaining internal steel pipework at 70°C.